41. Lori has been asked to create a PWBS dictionary for the DePaolo program. Which of the following is not a possible element that could be included in her PWBS dictionary?
42. Adam is creating program schedule. He is trying to define the program components and the dependencies among those components. Adam realized that some of the program components will be needed only if certain conditions are met along the program schedule. Which diagramming method should Adam use to display those components?
43. Josh is a program manager who likes to keep on top of things at You Want It - We Build It Industrial. So when he’s telling his project managers to prep project plans for each project based on the most current and available information, having them make changes as new information comes in, what technique is he using?
45. Fae’s program, Don’t Be Boxed Out, is in the planning stage, and she would like to determine the resource requirements for her program. What process should Fae perform?