PgMP Program Manager Exam Prep

Category - Program Management

Lori has been asked to create a PWBS dictionary for the DePaolo program. Which of the following is not a possible element that could be included in her PWBS dictionary?
  1. Detailed budget for each project within DePaolo
  2. A list of schedule milestones for DePaolo
  3. Cost Estimate
  4. List of resources Lori and her team will need to complete DePaolo
Explanation
Answer - A - A detailed budget for each project within the program will not be included in a PWBS Dictionary.

Key Takeaway: A PWBS dictionary contains detailed information about the PWBS components. The PWBS may include the following information: a code identifying the component, list of schedule milestones, a cost estimate, list of possible resources needed to complete the program, statement of work, the name of the project manager or key principle team members, and/or a list of quality requirements.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz