46. The Scope Definition process generates which of the following:
  1. Scope management plan
  2. Preliminary program scope statement
  3. Benefits realization plan
  4. PWBS
47. What are the components at the lowest level of a program WBS hierarchy called?
  1. Program deliverables
  2. Program packages
  3. Work packages
  4. Schedule activity
48. The Program Schedule Management Plan is an output of which of the following processes?
  1. Program Schedule Development
  2. Program Planning
  3. Program Schedule Planning
  4. Program Schedule Definition
49. Boris is the manager of the Yes I Read book-publishing program. He has decided to procure book cover images from a digital design company for the next fiscal year. Currently Boris has no idea how many books he will publish in the year. What type of contract is most suitable for Boris to use when he signs with the digital design company?
  1. Fixed price
  2. Time and material
  3. Cost plus fee
  4. Lump sum
50. Which is NOT included in the Communication Planning process?
  1. Determine the technology requirements for the communication
  2. Determine the information needs of the program stakeholders
  3. Determine who needs what information and when
  4. Issue a request for information, a request for proposal, and a request for quotation