What program Planning processes belong to Scope Management?
  1. Scope Definition and Schedule Development
  2. (PWBS) Create Program Work Breakdown Structure and Plan Scope
  3. Scope Definition and Scope Control
  4. Scope Definition and (PWBS) Create Program Work Breakdown Structure
Explanation
Answer - D - Scope Definition and Program Work Breakdown Structure(PWBS) belong to Scope Management.

Key Takeaway: Overall, the scope management plan lays out general guidelines for creating a PWBS for a given program. A solid scope definition is, of course, a primary requirement in setting the guidelines and plans for any PWBS. Without defining the scope, a program cannot be planned in any capacity.