Adam is creating program schedule. He is trying to define the program components and the dependencies among those components. Adam realized that some of the program components will be needed only if certain conditions are met along the program schedule. Which diagramming method should Adam use to display those components?
  1. Precedence diagramming method (PDM)
  2. Conditional diagramming method (CDM)
  3. Arrow diagramming method (ADM)
  4. Forceful diagramming method (FDM)
Explanation
Answer - B - Adam should use the conditional diagramming method, or CDM.

Key Takeaway: The conditional diagramming method is designed to handle conditional dependencies of components in program scheduling. ADM and PDM cannot handle conditions and therefore, cannot be used in this scenario. There is no such thing as the forceful diagramming method.