56. Jordi Brahms is double checking to make sure he has all the inputs to the Risk Management Planning and Analysis process accounted for. Which of the following is NOT an input to the Risk Management Planning and Analysis process?
  1. PWBS
  2. Risk response plan
  3. Program schedule
  4. Program budget
57. Marjory is a new program manager and she asks her boss Dixon what are the processes are in Program Risk Management? Dixon should say:
  1. Risk Management Planning and Analysis, and Risk Response Planning
  2. Risk Management Planning, Risk Identification, and Risk Analysis
  3. Risk Management Planning, Risk Identification, Qualitative Risk Analysis, Quantitative Risk Analysis, and Risk Response Planning
  4. Risk Management Planning and Analysis and Risk Monitoring and Control
58. Which of the following processes uses Regulations and legislation as an input?
  1. Risk Identification
  2. Quality Planning
  3. Communication Planning
  4. Risk Response Planning and Analysis
59. Howie Dix is planning risk management for his program Ventriloquism Is Easy. Which of the statements below is FALSE?
  1. A risk register is an input to both qualitative risk analysis and quantitative risk analysis.
  2. Quantitative risk analysis can be performed only on the risks on which the qualitative risk analysis has already been performed.
  3. An updated risk register is the output of both qualitative risk analysis and quantitative risk analysis.
  4. Qualitative risk analysis is usually performed before the quantitative risk analysis.