36. Finnian is the program manager of a program called Too Cute for Comfort. Annika’s Pink Emporium, the program’s sponsor, is asking for the program team directory. Which process does Finnian need to perform to create this document?
  1. Initiate Program
  2. Initiate Projects
  3. Initiate Team
  4. Authorize Projects
37. Which is NOT a tool or technique common to most of the program management process?
  1. Delphi
  2. Expert judgment
  3. Policies and procedures
  4. Meetings
38. Secondary risks are:
  1. Risks that result from responses to the originally identified risks
  2. Residual risks
  3. Risks which have medium or low priority
  4. Risks that have been mitigated
39. Which of the following is not included in the program scope management plan?
  1. How to create the PWBS from the scope
  2. A description of how the PWBS will be approved and managed
  3. A process for how to handle requests for changes to the scope statement
  4. A benefits analysis
40. Howard’s program, Ferocious, has been approved. Now, Howard needs to create his Program Work Breakdown Structure, or PWBS. Which if the following are necessary input items to create the PWBS?
  1. Benefits realization plan
  2. Program scope statement
  3. Scope management plan
  4. All of the above