6. What is a stage gate process?
  1. A form of rolling wave planning
  2. Formal deliverable acceptance
  3. Phased project procedure where at the end of each stage management debates whether or not to continue the project
  4. Scope management technique
  5. A way of assessing projects using metrics
7. Doris Mayweather is managing the execution of the Would You Be Mine? program, and she wants to make forecasts about the expected progress and performance of the program. Which process should she perform?
  1. Performance Reporting
  2. Extrapolate Performance
  3. Monitor and Control Program Work
  4. Direct and Manage Program Execution
8. While Howard is gathering information on potential risks for Ferocious, he decides to use a technique to reach a consensus among all the experts who are weighing in on the program. He facilitates a program for sharing ideas and information anonymously. What technique is Howard using?
  1. SWOT Analysis
  2. Brainstorming
  3. Delphi technique
  4. Surveys
9. Which process group does performance reporting belong to?
  1. Monitoring and Controlling
  2. Performance
  3. Planning
  4. Executing
10. Brendan is managing a large IT project at a venture-backed startup that is scaling up. The project requires frequent change requests due to multiple IT initiatives simultaneously happening within the growing firm. A particular business manager with a lot of clout is pressing Brendan to make changes that may not only impact the project’s scope, but cost and timeline as well. Which exemplifies the best route for Brendan to take?
  1. He could use corrective action.
  2. He could suggest the formation of a change control board.
  3. He could employ dynamic programming.
  4. He could hold a kickoff meeting.
  5. He could consult the scope creep committee.