Which of the following is not included in the program scope management plan?
  1. How to create the PWBS from the scope
  2. A description of how the PWBS will be approved and managed
  3. A process for how to handle requests for changes to the scope statement
  4. A benefits analysis
Explanation
Answer - D - A benefits analysis is not included in the program scope management plan.

Key Takeaway: The program scope management plan is generally a plan for how the scope will be identified, administered, and controlled throughout the life of the program-or, how the scope will be managed. The plan should include: a process to create the PWBS from the scope, a description of how that PWBS will eventually be approved and managed, how to create a more detailed program scope statement, and a process for how any changes to the preliminary scope statement will be handled.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz