Finnian is the program manager of a program called Too Cute for Comfort. Annika’s Pink Emporium, the program’s sponsor, is asking for the program team directory. Which process does Finnian need to perform to create this document?
  1. Initiate Program
  2. Initiate Projects
  3. Initiate Team
  4. Authorize Projects
Explanation
Answer - C - Finnian needs to perform the Initiate Team process to create the program team directory.

Key Takeaway: The program team directory should contain a list of the program’s key team members and any relevant information, such as the team members’ roles, contact information, and their responsibilities within the program. The program directory is only an output of the Initiate Team process.