Howard’s program, Ferocious, has been approved. Now, Howard needs to create his Program Work Breakdown Structure, or PWBS. Which if the following are necessary input items to create the PWBS?
  1. Benefits realization plan
  2. Program scope statement
  3. Scope management plan
  4. All of the above
Explanation
Answer - D - All of the above are necessary input items to create the PWBS.

Key Takeaway: In order to execute a large program, it is necessary to break down the scope into manageable parts, called the program work breakdown structure. Creating the PWBS is an integral part of program management. It is a deliverable-oriented decomposition of the work that must be performed to accomplish the objectives of the program. The PWBS should represent the program’s total scope.