Which is NOT included in the Communication Planning process?
  1. Determine the technology requirements for the communication
  2. Determine the information needs of the program stakeholders
  3. Determine who needs what information and when
  4. Issue a request for information, a request for proposal, and a request for quotation
Explanation
Answer - D - Issue a request for information, a request for proposal, and a request for quotation.

Key Takeaway: The Communication Planning process is best remembered by the four Ws: what information is needed, when, who needs it, and who will deliver it. To do this, it will be necessary to know the program scope and the proper requirements to plan communication, such as information for the proper stakeholders and technology requirements of the organization.