PgMP Program Manager Exam Prep

Category - Program Management

The Program Schedule Management Plan is an output of which of the following processes?
  1. Program Schedule Development
  2. Program Planning
  3. Program Schedule Planning
  4. Program Schedule Definition
Explanation
Answer: C - Program Schedule Planning generates the Program Schedule Management Plan.

Key Takeaway: The Program Schedule Planning process generates two outputs: a Program Schedule and a Schedule Management Plan. Remember that the creation of a program schedule is basically road mapping how you will ultimately execute the program. schedule management involves defining the program components (component definition), configuring the order in which the components will be executed (component sequencing), figuring out how much time it will take to complete each component (component duration estimating), and assigning an accurate timeline for completing the components (component scheduling).
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz