The Scope Definition process generates which of the following:
  1. Scope management plan
  2. Preliminary program scope statement
  3. Benefits realization plan
  4. PWBS
Explanation
Answer - A - The Scope Definition process generates the scope management plan.

Key Takeaway: Scope Definition generates both a detailed scope statement and the scope management plan. The detailed scope statement defines in detail what is-and is not-included in the program. It becomes the cornerstone for all program decision making during the rest of the program’s life cycle. The program scope management plan literally describes how the program scope will be managed throughout the life of the program.