Which of the following steps, in correct sequence, are used in the project management process?
  1. Forming, storming and norming
  2. Storming, forming and norming
  3. Planning/design, Initiation, implementation, monitoring and completion
  4. Initiation, planning/design, implementation, monitoring and completion
Explanation
Answer: D - Initiation, planning/design, implementation, monitoring and completion are the steps of the project management process in correct sequential order. These steps are closely aligned with those of the problem solving process (defining the problem, looking at and deciding among options, implementation and evaluation).

Category: Strategic management and technology - Managing projects
Was this helpful? Upvote!