Which of the following are tolerance areas?

  1. Change
  2. Issues
  3. Quality
  4. Benefits
  1. 1,2
  2. 2,3
  3. 2,4
  4. 3,4
Explanation

Answer: D - 3, 4. Quality and benefits are tolerance areas, along with Time, Cost, Scope, and Risk.

Key takeaway: Tolerances can only be set on measurable areas and involve +/- amounts on planned costs, dates, measurable benefits, and the like. Harder to measure tolerances, such as scope or risk, can be expressed in the form of which requirements may be sacrificed, or the projected cost of the risks.