Who is responsible for communicating with stakeholders?
  1. Executive
  2. Senior User
  3. Project Manager
  4. Project Board
Explanation
Answer: D - The Project Board. It is the responsibility of the entire board to liaise with stakeholders.

Key takeaway: The precise methods of communication should be documented in the Communication Management Strategy. The Project Board may also call upon Project Assurance for advice in this area.