Which statement is correct?
  1. Quality metrics are an input to Perform Quality Control
  2. Quality metrics are an output of Perform Quality Assurance
  3. Quality metrics are an input to Quality Planning
  4. Quality metrics are an output of Quality Planning
Explanation
Answer -D - Quality metrics are an output of Quality Planning.

Key Takeaway: Quality metrics define what something is (a feature, or characteristic) and how, exactly, it will be measured by quality control. The metrics that you and the program/project group set during quality planning will be used later in quality assurance. Because of this, it is important to use quantifiable criterion.