Josh is working on a brand new program, Need a Date!, and he’s going to be performing the following processes for the first time for his program. Which is the first process he should perform?
  1. Create PWBS
  2. Schedule Development
  3. Scope Definition
  4. Transition Planning
Explanation
Answer - C - Josh needs to perform Scope Definition first.

Key Takeaway: Scope Definition generates the program scope statement. The program scope statement is used to create the PWBS and to perform Transition Planning. And Schedule Development uses the PWBS as an input. So when performing these processes for the first time, Scope Definition must be performed first in order to be able to perform the other processes.