According the Prince2 principles, the scope of a plan is defined by:
Answer: D - According the Prince2 principles, the scope of a plan is defined by the set of products to be delivered. Key takeaway: One of the principles of a PRINCE2 project is Focus on Products. It is the products which define a project (as opposed to the activities or processes). As such, the scope of the project is also defined by the products to be delivered.