What name is given to the piece of work performed by a Team Manager for the Project Manager?
  1. Work Package
  2. Team Plan
  3. Product Description
  4. Project Product Description
Explanation
Answer: A - Work Package.

Key takeaway: The idea of a Work Package is to allow the Team Manager to handle it in whatever way they deem necessary. This could mean not using PRINCE2 methods. Essentially, it is an interface between a PRINCE2 project and the project's product suppliers (both internal and external).