Which role is responsible for defining and verifying user requirements and expectations?
  1. Executive
  2. Senior User
  3. Project Assurance
  4. Team Manager
Explanation
Answer: B - Senior User.

Key takeaway: The three Project Board roles have different responsibilities. While the Executive retains control and is responsible for the business requirements, the Senior User and Senior Supplier are responsible for the committal of user and supplier resources respectively, and are the primary point of contact for any user/supplier issues. This includes defining and verifying requirements.