PgMP Program Management

Category - Domain 3

Which of the following structures displays the breakdown of project deliverables into smaller, more manageable components?
  1. (PBS) Project breakdown structure
  2. (WBS) Work breakdown structure
  3. (HWS) Hierarchical work structure
  4. (SND) Schedule Network Diagram
Explanation
Answer - B - The work breakdown structure breaks down project deliverables into smaller, more manageable components.

Key Takeaway: A work breakdown structure, or WBS, is a detailed decomposition of the work that will be performed in order to accomplish the goals of a program. Usually, the WBS is broken down into a hierarchy-that is, in the order of the most critical components to program completion to the least critical.