Seamus McTroid’s program, World Domination, is in phase five. Seamus wants to make archives of the information from the constituent projects. Which process should Seamus perform?
  1. Administrative Closure
  2. Close Program
  3. Contract Closure
  4. Component Closure
Explanation
Answer - D - Seamus should perform the Component Closure process to make archives of the information from the constituent projects.

Key Takeaway: The Component Closure process is utilized to oversee the closure at the project level. By using the project management processes, this process ensures that the projects have been properly closed. Completing the Component Closure process will produce the following outputs: certificate of program completion, communication messages, updates to resource availability, and project and program archives.