Civil Engineering PE

Category - Scheduling

Which of the following project management tools is used to present a snapshot of the progress of the project?
  1. Work Breakdown Structure (WBS)
  2. Milestone chart
  3. Program Evaluation and Review Technique (PERT) Chart
  4. All of the above
Explanation
Answer: B - A milestone chart is used to present a snapshot of the progress of a project. Project milestones are important events in the project, as they represent critical points in the project, such as the submission of a design report or the date by which a wastewater treatment plant must be commissioned. Milestone dates are usually defined in the project contract or are established during the project kick-off meeting with the client.