Which of the following best describes the cut construction method for earth retaining systems?
  1. Walls are constructed from the base of the wall up, following excavation operations
  2. Walls are constructed from the top down to the base, concurrent with excavation operations
  3. A. and B.
  4. None of the above
Explanation
Answer: B - The cut construction method for earth retaining system constructs walls from the top, going down to the base (top-down construction), concurrent with excavation operations. Fill construction refers to a method used to construct a wall from the base to the top (bottom-up construction). The “cut” and “fill” designations refer to the manner by which the wall is constructed, not the nature of the earthwork performed during the construction process.