Which of the following documents is NOT produced within a PRINCE2 project?
  1. Lessons log
  2. Project mandate
  3. Project manager role description
  4. Stage plan
Explanation
Answer: B - Project mandate. This is the document that triggers the initiation of a project.

Key takeaway: The project mandate comes from the authority that is commissioning the project and its creation is a pre-project activity.
Was this helpful? Upvote!