Which role is responsible for committing supplier resources to the Stage Plans?
  1. Executive
  2. Senior Supplier
  3. Project Manager
  4. Corporate or Programme Management
Explanation
Answer: B - Senior Supplier. This role is the supplier representative on the Project Board.

Key takeaway: When appointing board members, one of the important qualities they must have is the relevant authority to commit resources as required by the project. Each Project Board member is responsible for committing resources from their own area.