PgMP Program Management

Category - Domain 5

Which is NOT part of the Integrated Change Control process?
  1. Approve Change requests
  2. Implement the approved change requests
  3. Determine if a change has occurred
  4. Escalate the change requests
Explanation
Answer - B - Implement the approved change requests is not part of the Integrated Change Control process.

Key Takeaway: The Integrated Change Control process coordinates changes in areas such as: cost, schedule, scope, and quality across the whole program. This ensures that changes have gone through a review process before being implemented. The Integrated Change Control Process includes the following tasks: approval and refusal of change requests, Escalate the change requests, determine if a change has occurred, influence factors that create changes, and determine how and when the changes will be applied.
Was this helpful? Upvote!