PgMP Program Management

Category - Domain 6

Which of the following processes does the Closing process group consist of?
  1. Close Program, Close Projects, and Contract Closure
  2. Contract Closure, Component Closure, and Transition Benefits
  3. Close Program, Administrative Closure, and Contract Closure
  4. Close Program, Component Closure, and Contract Closure
Explanation
Answer - D - The Closing process group consists of the Close Program, Component Closure, and Contract Closure processes.

Key Takeaway: Closing a program is the formal acceptance of the program outcome. The Closing process group finalizes closure of a program and all of its constituent projects, closes all program activities, and closing all contracts that were opened in the program and projects.