Which of the following is NOT an input to the Resource Control process?
  1. Performance reports
  2. Resource management plan
  3. Expenditure reports
  4. Program budget
Explanation
Answer - C - Expenditure reports are not an input to the Resource Control process.

Key Takeaway: Resource Control manages all program and project resources and their associated costs, in accordance with the original program management plan.