Which is NOT an input item to the Scope Definition process?
  1. Preliminary program scope statement
  2. Program charter
  3. Program scope statement
  4. Benefits realization plan
Explanation
Answer - C - Program scope statement is not an input to the Scope Definition process.

Key Takeaway: Preliminary program scope statement, program charter, and benefits realization plan are all inputs to the Scope Definition process. Program scope statement is an output of the Scope Definition process.