PgMP Program Management

Category - Domain 3

Which process must be performed to develop a contract statement of work?
  1. Plan Program Contracting
  2. Plan Program Purchases and Acquisitions
  3. Develop Statement Work
  4. Develop Program Management Plan
Explanation
Answer - B - Performing the Plan Program Purchases and Acquisitions process will develop a contract statement of work.

Key Takeaway: A contract statement of work, or SOW, is an output of the Plan Program Purchases and Acquisitions process. It is a document that describes in detail the products or services that the seller will deliver to the client. Only through this process can a contract statement of work be developed. It then becomes an input to the Plan Program Contracting process.
Was this helpful? Upvote!
Login to contribute your own answer or details