What are the two types of progress controls provided by PRINCE2?

  1. Stage-driven
  2. Tolerance-driven
  3. Time-driven
  4. Event-driven
  1. 1, 2
  2. 1, 4
  3. 2, 3
  4. 3, 4
Explanation

Answer: D - Time-driven and event-driven.

Key takeaway: Time-driven controls occur at pre-defined intervals and include things like the Checkpoint report and Highlight report. Event-driven controls happen when a specific event triggers them, such as the end of a stage.