Dixon is performing the Interface Planning process for his Art-2 Unit program. Which is not a tool or technique that can be used for this process?
  1. Pareto diagram
  2. Organizational theory
  3. Stakeholder analysis
  4. Human resource practices
Explanation
Answer - A - Pareto diagram is a tool that cannot be used in the Interface Planning process.

Key Takeaway: Throughout the life of a program and its projects, the program may be interacting with several different programs in the organization or even with outside factors. Interface Planning plans for the interfaces of these interactions, mapping how the relationships between programs will be managed. Organizational theory, stakeholder analysis, and human resource practices are all tools and techniques that can be used for the Interface Planning process.