Moris Lipswitch, the program sponsor, is asking for the performance measurement baseline. Which of the following are three components of a performance measurement baseline?
Explanation
Answer - D - Scope baseline, schedule baseline, and cost baseline, are all components of a performance measurement baseline.
Key Takeaway: A baseline is a reference plan, either original or modified, for components against which performance deviations are measured. Such components are schedule, scope, and cost. The actual performance of a program is evaluated by comparing it to the performance measurement baseline.