Which knowledge area does Transition Planning belong to?
  1. Communication Management
  2. Procurement Management
  3. Human Resource Management
  4. Integration Management
Explanation
Answer - D - Transition Planning belongs to the Integration Management knowledge area.

Key Takeaway: The following Planning processes belong to Integration Management: Transition Planning, Develop Program Management Plan, Interface Planning, and Resource Planning. The Integration Management Knowledge area includes program management tasks that deal with the big picture of program management tasks. This includes identifying, uniting, and coordinating processes and projects across process groups and different knowledge areas.