Civil Engineering PE

Category - Temp Structures

For which of the following purposes during construction is the ground frozen?
  1. Temporary underpinning
  2. Cut off the flow of groundwater
  3. Stabilize the ground for tunnel excavation
  4. All of the above
Explanation
Answer: D - During construction, the ground may be frozen to temporarily underpin a structure, cut off the flow of groundwater, or stabilize the ground for tunnel excavation purposes. The purpose of freezing the ground is to change the water within the soil into a solid, impermeable ice wall. A common method used to freeze the ground is to place vertical rows of freezepipes in the soil and remove the heat energy through the pipes.
Was this helpful? Upvote!
Login to contribute your own answer or details