Which role(s) has/have ultimate authority on the Project Board?
  1. Senior Supplier
  2. Senior User
  3. Executive
  4. Joint authority
Explanation
Answer: C - Executive. The project is ultimately controlled and paid for by the business, which is represented by the Executive.

Key takeaway: Although the Project Board generally makes decisions together, it is not a democracy. The Senior Supplier and Senior User can be overruled by the Executive, even if they are both united against him.
Was this helpful? Upvote!
Login to contribute your own answer or details