Which role confirms acceptance of the Project Product?
  1. Project Assurance
  2. Corporate or Programme Management
  3. Project Manager
  4. Executive
Explanation
Answer: D - Executive. The Executive has ultimate authority within the project.

Key takeaway: Since the Executive is the owner of the Business Case and is responsible for ensuring the case remains valid throughout the life of the project, it is also their responsibility to provide final acceptance of the Project Product.