Doris Mayweather is managing the execution of the Would You Be Mine? program, and she wants to make forecasts about the expected progress and performance of the program. Which process should she perform?
  1. Performance Reporting
  2. Extrapolate Performance
  3. Monitor and Control Program Work
  4. Direct and Manage Program Execution
Explanation
Answer - C - Doris should perform the process Monitor and Control Program Work which produces forecasts as an output.

Key Takeaway: The Monitor and Control Program Work process gathers program performance information and measures it in order to make improvements. The outputs of this process are change requests, forecasts, and communication messages for stakeholders.