Which of the following is NOT a PRINCE2 process?
  1. Directing a Project
  2. Assessing a Project
  3. Controlling a Stage
  4. Closing a Project
Explanation
Answer: B - Assessing a Project. There is no such process within PRINCE2.

Key takeaway: Assessment is ongoing throughout all aspects of a PRINCE2 project. It is done at all levels, often with reports (e.g. Highlight Reports, Checkpoint Reports) or as a basic function of a role (e.g. Project Assurance).