Which Stage does PRINCE2 recommend always be used?
  1. Initiating a Project.
  2. Closing a Project.
  3. Starting up a Project.
  4. Implementing a Project.
Explanation
Answer: A - Initiating a Project. A PRINCE2 project should consist of this stage and one other.

Key takeaway: The Initiating a Project stage takes care of much of the initial project admin. It also allows for the project to be defined and provides an end of stage point for the business plan to be approved (in line with the principle of continued business justification) and the project to proceed to the next stage.