Which is NOT an input to the Direct and Manage Program Execution process?
  1. Program schedule
  2. Implemented change requests
  3. Approved change requests
  4. Program management plan
Explanation
Answer - B - Implemented change requests are not an input to the Direct and Manage Program Execution process.

Key Takeaway: The Direct and Manage Program Execution process manages various interfaces in the project to execute the program work smoothly with the objective of delivering the planned benefits. The input of the Direct and Manage Program Execution process includes the program management plan and the program schedule. Approved change requests are integrated with the program management plan and are therefore considered an input to the process, but implemented change requests are included in the output of the Direct and Manage Program process.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz