In which phase of the program life cycle is the infrastructure for a program established?
  1. One
  2. Two
  3. Three
  4. Four
Explanation
Answer - C - The infrastructure for a program is established in phase three of the program life cycle.

Key Takeaway: The program life cycle consists of: Pre-program setup, Program setup, Establishing Program Infrastructure, Delivering Benefits, and Closing the Program. The infrastructure for a program is established in phase three of the life cycle, aptly named “Establishing Program Infrastructure.”