Which of the following are part of the perform quality control process? Select all that apply:
  1. Assessing the effectiveness of project control systems
  2. Performing re-work to meet quality standards
  3. Authorize work
  4. Make payments to a vendor
  5. Monitor the effectiveness of risk response plans
Explanation
Answer: A, B - Assessing the effectiveness of project control systems and performing re-work to meet quality standards are both part of the Quality Control process.
Monitor the effectiveness of risk response plans is part of the Risk Monitoring and Control process.
Authorizing Work and Making Payments are part of the Contract Administration process.

Key takeaway: It is important for the PMI exam to know where these processes fit in. These questions are not going to be exciting, but they are good to practice.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz