True or false: Completing re-work is an accepted quality control process.
  1. True
  2. False
Explanation
Answer: True. Re-work sounds like something project managers want to eliminate, and it is! However, it is necessary in many projects.

Key Takeaway: The key is to be keeping a close enough eye on quality to ensure that the amount of re-work is small relative to the size of the project. We have noticed that some project managers will go out of their way to hide the fact that any re-work needs to be done. This is a violation of professional standards, but also a reflection of fear of this term that has cropped up in PM circles.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz