Mario Luigi is a program manager and he wants to capture lessons learned before he can perform a certain process. Which process is Mr. Luigi referring to?
  1. Make Archive
  2. Component Closure
  3. Administrative Closure
  4. Contract Closure
Explanation
Answer - B - Mr. Luigi wants to capture lessons learned before he can perform the Component Closure process.

Key Takeaway: It is important to capture lessons learned during the program closure. Both positive and negative, lessons learned are used to support program and organizational improvements in the future. They are archived by using the program/project management information system and they are an input to the Component Closure process.