Which process does NOT belong to the Executing process group?
  1. Perform Quality Assurance
  2. Information Distribution
  3. Cost Estimating and Budgeting
  4. Acquire Program Team
Explanation
Answer - C - Cost Estimating and Budgeting do not belong to the Executing process group.

Key Takeaway: The Executing process group drives the program work, in accordance with the program management plan and its subsidiary plans. In essence, it is the same thing as executing the program management plan. The executing process group includes acquiring the resources, contractors, staff, and suppliers needed to execute the program; developing the program team and ensure proper quality standards; and making sure that all program stakeholders receive any relevant program information.