PgMP Program Management

Category - Domain 4

Which of these is performed first?
  1. Create PWBS
  2. Program Schedule Development
  3. Develop Program Team
  4. Acquire Program Team
Explanation
Answer - A - Create PWBS is performed first.

Key Takeaway: Program Schedule Development, Develop Program Team, and Acquire Program Team all use the PWBS as an input item. Because the PWBS is needed before you can do any of the other things, creating the PWBS should always be your first priority when starting new programs.
Was this helpful? Upvote!
Login to contribute your own answer or details